Detailed design, procurement, and construction (EPC) services for a $300 million coal-fired power plant regulatory program including fly ash, bottom ash, and water management conversions.
Detailed design and structural dynamics engineering evaluation to analyze an existing paper machine dryer section for an unbalance issue at an existing facility.
This effort included the detailed design, material procurement, construction planning and construction management for a $3 million brownstock washing system upgrade.
This effort included the detailed design, permitting, and on-site construction support for a $75 million greenfield plant to produce food-grade vegetable oil.
The project included front-end engineering and detailed design for a multi-year facility expansion at a honeycomb scrubber plant to facilitate a six-fold increase in production capacity.
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
This effort included the review of process drawings, on-site facilitation of dust hazard analysis using a what-if method, as well as review of applicable NFPA standards for a wood-products facility.
The effort included the front-end engineering and detailed design services for installing a 15 TPD Green Hydrogen Production and Liquefaction Plant on a greenfield site.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.