This effort included the detailed design, permitting, and construction support for the balance of plant (BOP) systems on a 1400 BPD facility converting woody biomass into renewable fuels.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.
This project effort included detailed design and construction support for a turnkey, full-scale Ethylene Oxide production facility along the Delaware River.
This effort included the FEED, detailed design, permitting, and construction support for a 6500 BPD Renewable Diesel Plant, utilizing Haldor Topsoe technology.
This effort was an independent technical review of a propylene glycol facility design combining existing, proven technologies and new proprietary reactor technology. The plant design converts low-value waste biodiesel crude glycerol ...
This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.