This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Detailed design and structural dynamics engineering evaluation to analyze a 4000-hp existing power plant ID fan for an unbalance issue at an existing facility.
This effort included the FEED, detailed design, permitting, and construction support for a 6500 BPD Renewable Diesel Plant, utilizing Haldor Topsoe technology.
This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
This effort included the detailed design, permitting, and on-site construction support for a $75 million greenfield plant to produce food-grade vegetable oil.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.