This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
The project included front-end engineering and detailed design for a multi-year facility expansion at a honeycomb scrubber plant to facilitate a six-fold increase in production capacity.
This effort included the detailed design, permitting, and construction support for a $400 million, 850,000 sq. foot state of the art particleboard manufacturing plant.
Isomer provided detailed design engineering, permitting, and construction support for a renewable natural gas facility located at the Anson County Landfill.
Isomer provided detailed design for a $6 million battery storage project to enhance grid stability by providing additional capacity during times of peak consumption for the city utility.
Detailed design, procurement, and construction for a $100 million fly ash, bottom ash, and pyrites handling and transport conversion EPC project to meet Coal Combustion Residuals (CCR) environmental regulations.
Detailed design and structural dynamics engineering evaluation to analyze a 4000-hp existing power plant ID fan for an unbalance issue at an existing facility.
This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.